Click to enlarge |
The winner of the bid will replace the current antiquated facility at LaGuardia Airport—recently compared by Vice President Joe Biden to that of a third world country—with a state-of-the-art successor.
The new terminal will also be larger, 1.3 million square feet, more than a third bigger than the present building. In addition it will likely feature more amenities and revenue-generating operations such as retail space and food concessions.
In 2012, LaGuardia handled 25.7 million passengers. Port Authority officials forecast that 34 million travelers will use the airport by 2030. More than half of those passengers are expected to use the new Central Terminal Building, the Port Authority said.
The project is expected to generate $112 million in wages, the Port Authority said. The federal government will reimburse 95 percent of the project's expenditures.
The project will be done in phases, the first of which began last year when the Port Authority began building a new $82.9 million parking garage that will rise on the east side of the terminal next to the Delta Air Lines terminal.
That 1,100-car garage, and another that is slated to be built on the west side of the terminal, will allow the airport's main garage to be demolished to make way for the new terminal building, which will rise on that site.
In all, the Port Authority has pledged to make $1.2 billion in upgrades to the airport that will lay the infrastructure for the new terminal building.
The amount of traffic that passes through the terminal has vastly exceeded its 8 million passengers a year it was designed to handle. In 2012, that figure swelled to 25.7 million travelers and by 2030, the Port Authority projects at least 34 million will pass through the terminal each year.
The new terminal will be 1.3 million square feet and boast 35 gates. The current terminal also has 35 gates but at 835,000 square feet, it is nearly 40% smaller than its planned successor.
The new building would mark a vast improvement on the existing facilities, which opened in 1964 and are universally considered to be antiquated with undersized security and baggage processing areas, as well as undersized food concession and retail areas, that in most airports are both big amenities and revenue generators.
Other work being completed includes upgrades to Terminals C and D for Delta Air Lines, the airport's largest carrier. Delta recently opened a new 630-foot-long pedestrian bridge and installed a moving walkway.
Also 2,000 iPads are being installed in both terminal waiting areas, allowing passengers to order meals that are delivered to them.
The Port Authority has shortlisted two teams of architects and contractors to design, build, finance, and operate the 1.3 million-square-foot Central Terminal Building.
The project also includes replacing frontage roads and a central heating and refrigeration plant, as well as operating and maintaining the existing Central Terminal during the construction period and the new building for a specified term.
Click to enlarge |
The two finalists competing to win the $3.9 billion job to renovate the terminal, agreed to extend their bids, - which was supposed to conclude in April - to the end of this month, giving the Port Authority time to reconcile the design competition's recommendations and the existing plans to redevelop the facility.
The remaining finalists include the following architecture and construction firms:
- LaGuardia Gateway Partners, which includes Skanska USA Building, Skanska USA Civil, Meridiam Infrastructure, Tishman Construction, Parsons Brinckerhoff and Vantage Airport Group;
- LGA Central Terminal Consortium, a joint venture of AĆ©roports de Paris, TAV Construction, Tutor Perini, Suffolk Construction, STV, Arup and Kohn Pedersen Fox.
The project includes demolishing the existing terminal and its four concourses, garage, Hangar 1, and frontage roads; building temporary facilities; and designing and building the Central Terminal Building. It also includes constructing a central heating and refrigeration plant, utilities for the new building, hydrant fueling within the project site limits; as well as operating, maintaining and managing the existing terminal and temporary facilities during construction.
The winning bidder will pay for the building, but pocket a cut of the revenue from airline leases and rents from stores and restaurants.
The Port Authority is expected to select the winning project team at the end of this month.
Visit Our Sponsors
Page Views
Since October 1, 2011
No comments:
Post a Comment